When you attempt to run a planned migration of a recovery plan that contains a storage policy protection group, the recovery plan fails because of an unfinished synchronization of changes to the protection group.
Problem
Cause
When you run a planned migration of a recovery plan that contains a storage policy protection group, Site Recovery Manager checks whether the protection groups are synchronized on both of the protected and recovery sites before it runs the recovery plan.
If the protection group is synchronized on both sites, the planned migration begins. If the protection group is not synchronized on both sites, you see the error message.
Solution
- Close the error message and click Finish again.
- (Optional) If the error persists, cancel the planned migration, wait a short time, and attempt to run the planned migration again.