Packages can be moved from one Application to another. When similar Package requirements across Applications exist, you can use the move functionality.

When you move a Package which has an assigned entity, the entity also moves to the target application.

Prerequisites

Ensure that the Package you want to move has no CURRENT marker.

If the Package has a CURRENT marker, you must first unset the marker and then move the Package. Unset the CURRENT Marker on a Package

Procedure

  1. From App Volumes Manager, go to INVENTORY > Packages.
  2. Click the Package you want to move.
  3. Click Move.
    If the Version you are moving is the only Version of the Previous Application, you can delete the Application if you want.
  4. Select the Application that you want to move the Package to from the Application drop-down menu.
    If there are Assignments for the Package you are moving, the Assignments are listed.
  5. Click Move.
  6. (Optional) On the Delete Application window, click Delete.
    If the Package you want to move is the only Package of the previous Application, then you can delete the Application. Deleting the Application also results in deleting the assignments to the Application.

What to do next

Navigate to the Application to which you moved the Package and review the Package information.