As an App Volumes administrator, when you mark a Package as CURRENT and you select the Assignment Type as Marker, the entity to which the Packaged Application is assigned always receives the latest version of the Application.

  • Only one Package in an Application can be set as CURRENT.
  • All entities with the Marker assignment type receive the Package marked as CURRENT.

Prerequisites

The Package that you want to mark as CURRENT must have completed the packaging process.

Procedure

  1. From App Volumes Manager, go to INVENTORY > Packages.
  2. Click the Package that has completed the packaging process.
    Status of the Package, which has completed the packaging process, is Enabled.
  3. Review the Package information and click Set CURRENT.
  4. On the Confirm Set CURRENT window, click Set CURRENT.
    Package is marked as CURRENT.