After the inter-rack switch connections are in place, power on the additional rack.

Procedure

  1. Power on the additional rack.
  2. Ensure that you can ping a host on rack 2 from the first rack.
  3. Verify that the ports on the inter-rack switches on the additional rack are up.
  4. Verify that the link connectivity LED between the racks is up.