After you have migrated hosts to the NSX-T Data Center environment, confirm that the new environment is working correctly. If everything is functioning correctly, you can finish the migration.

Important: Verify everything is working and click Finish within the maintenance window. Clicking Finish performs some post-migration clean-up. Do not leave the migration coordinator in a unfinished state beyond the migration window.

Prerequisites

Verify that the NSX-T Data Center environment is working correctly.

Procedure

  1. Navigate to the Migrate Hosts page of the migration coordinator.
  2. Click Finish
    A dialog box appears to confirm finishing the migration. If you finish the migration, all migration details are cleared. You can no longer review the settings of this migration. For example, which inputs were made on the Resolve Issues page.