You need to configure the event processing task, in order to run the data-migration task which is enabled for run.

Procedure

  1. On the M&R Console, navigate to Centralized Management > Scheduled Tasks .
  2. Click Event-Processing.
    The scheduled event-processing tasks appears in the right pane.
  3. Select the event processing task.
    Figure 1. Scheduled Event-Processing example
  4. Click Run Now, to run the data-migration task which is enabled for run.