Procedure
- Deploy at least two NSX Edge nodes on Edge Cluster in Compute vCenter Server.
- Deploy NSX Edge Nodes from the NSX Manager UI. For more information about the sizing, see the Telco Cloud Platform 5G Edition Reference Architecture Guide 2.2.
- Connect NSX Edge Management interface (Network Interface-1) to Management Network port group on the edge distributed switch TCP_EDGE_MGMT_DVS.
- Connect the remaining Network Interfaces to the Trunk port group on TCP_EDGE_MGMT_DVS.
- Add both the NSX Edges into Overlay and VLAN Transport Zones. For more information about NSX Edge deployment, see Create an NSX Edge Transport Node.
- Create NSX Edge Cluster and add both the NSX Edge nodes. See Create an NSX Edge Cluster.