Before you begin a deployment, you must meet the requirements described in the following checklist.

Table 1. Before-you-begin checklist

Complete

Requirement

Description

Possess an understanding of the architecture and capabilities.

At a minimum, you must understand the concepts and architecture described in the following documents:

  • IP Manager Concepts Guide

  • IP Manager User Guide

  • IP Manager Reference Guide

  • Service Assurance Manager Introduction

  • Service Assurance Manager Adapter Platform User Guide

  • System Administration Guide

  • VMware Telco Cloud Service Assurance Installation Guide for SAM, IP, and ESM Managers

To improve your understanding, attend training courses. Typically, deployment requires the knowledge equivalent to what is provided in the training courses on:

  • IP Manager

  • Service Assurance Manager (Global Manager)

  • Service Assurance Manager Adapter Platform (Adapter Platform)

Obtain contact information for the deployment team.

The contact list should include titles, responsibilities, and contact methods for all team members.

Get nondisclosure requirements and negotiate an agreement.

Be aware of the requirements of the non-disclosure agreements that are in place for the deployment.

Develop schedules and set milestones for early deliverable.

Scheduling a software deployment varies based on the size and scope of the deployment and the organization’s requirements. Typical milestones might include:

  • Initial project meeting to define the deployment scope

  • Purchase of software

  • Project development begins

  • Installation in test environment complete

  • Testing complete

  • Installation in production environment complete

  • deployment goes live

Additional information on scheduling is beyond the scope of this guide.