After performing planned maintenance in your environment, verify that vRealize Operations Manager Cluster nodes and Remote Collectors are online and performing the data collection.

About this task

Verify the following configurations:

  • vRealize Operations Manager health

  • Self Monitoring dashboard

  • Authentication sources

  • Certificates

  • Licensing

Procedure

  1. Log in to vRealize Operations Manager by using the administration console.
    1. Open a Web browser and go to https://vrops-cluster-01.rainpole.local.
    2. Log in using the following credentials.

      Setting

      Value

      User name

      admin

      Password

      vrops_admin_password

  2. Verify that the cluster is online, all data nodes are running, and are joined to the cluster.
    1. In the left pane of vRealize Operations Manager, click Home and select Administration > Cluster Management.
    2. Verify that the vRealize Operations Manager Cluster Status is Online and High Availability mode is Enabled.
  3. If you have performed an upgrade or update, in the Nodes in the vRealize Operations Manager Cluster table, verify that the software version of all vRealize Operations Manager nodes is correct.
  4. Verify the State and Status of all vRealize Operations Manager nodes.
    1. In the cluster nodes table, verify that the State is Running and Status is Online for all nodes.
      • vrops-mstrn-01

      • vrops-repln-02

      • vrops-datan-03

      • vrops-rmtcol-01

      • vrops-rmtcol-02

      • vrops-rmtcol-51

      • vrops-rmtcol-52

    2. In the Adapter instances table, verify that Status is Data receiving for all instances.
  5. Verify the vRealize Operations Manager Cluster Health.
    1. In the left pane of vRealize Operations Manager, click Home
    2. On the Home page, from the from the Dashboard List drop-down menu, select vSphere Dashboards Library > Other > Self Health
    3. Verify that the status of all objects from the cluster is Green.




  6. Check that there are no critical alerts.
    1. On the vRealize Operations Clusters page, click the Alerts tab.
    2. Verify that there are no Critical alerts for the vRealize Operations Clusters objects.
  7. Verify that the authentication sources are valid and synchronization is successful.
    1. In the left pane of vRealize Operations Manager, click Home and select Administration > Authentication Sources.
    2. Select the Active Directory entry and click the Synchronize User Groups icon.
    3. In the Confirmation dialog box, click Yes.
    4. Verify that the synchronization is successful and that there are no errors. 




  8. Verify that the CA-Signed certificate is intact.
    1. In the left pane of vRealize Operations Manager, click Home and select Administration > Certificates.
    2. Verify that the Certificates are in intact.
  9. Verify that the License key is intact.
    1. In the left pane of vRealize Operations Manager, click Home and select Administration > Licensing.
    2. Verify that the valid License key is intact.