After you run a recovery plan for a planned migration or disaster recovery of VMware Identity Manager, you can restore the pre-recovery site by performing a failback.
Performing a planned migration or a disaster recovery from site A to site B is a two-step process: recovery and reprotect. Recovery results in Recovery Time Objective (RTO) downtime. After the recovery from site A to site B, the recovered virtual machines run on site B without protection until you perform the reprotect operation.
Reprotect runs in parallel with VMware Identity Manager services. Therefore, end users do not experience further downtime during the reprotect operation.
Prerequisites
- You performed a recovery, either as part of a planned migration or as part of a disaster recovery.
- The original protected site, site A, is running.
- You did not run reprotect after the recovery.
- If you performed a disaster recovery, you must perform a planned migration when the hosts and datastores on the original protected site are running again.
Procedure
- ♦ Follow the instructions provided in Site Recovery Manager Administration about performing a failback.
For example, for Site Recovery Manager 8.2, see Site Recovery Manager Administration 8.2