When the OVA deployment completes, you are redirected to stage 2 of the migration process to transfer the data from the source vCenter Server and start the services of the newly deployed target vCenter Server Appliance with an external Platform Services Controller.
Your window of downtime does not begin until you begin to set up the target appliance. You cannot cancel or interrupt the process until it completes with the shutdown of the source deployment. Your window of downtime ends when the target appliance starts.
Procedure
Results
The vCenter Server is migrated from Windows to a newly deployed target appliance. The source vCenter Server is powered off and the target appliance starts.
What to do next
Verify that your vCenter Server instances have migrated successfully. For verification steps, see Verify Your vCenter Server Appliance Upgrade or Migration Is Successful.
Complete the migration or upgrade of other vCenter Server instances in the configuration as needed. For information on upgrading vCenter Server instances on Windows, see Upgrade vCenter Server 5.5 on Windows or Upgrade vCenter Server 6.0 on Windows.
For post-migration steps, see After Upgrading or Migrating vCenter Server.