You must configure your load balancer before completing the initial installation of vRealize Automation, vRealize Orchestrator, or Workspace ONE Access.

Procedure

  1. Configure the F5, NSX, or NetScaler load balancer. See Configuring F5 BIG-IP, Configuring NSX, and Configuring Citrix NetScaler.
  2. Install and configure all the system components as instructed to in vRealize Automation, vRealize Orchestrator, and Workspace ONE Access installation and configuration documentation.
  3. Ensure that all nodes are in the expected state with the health monitor enabled in the load balancer after installation. The pool, service groups, and virtual server of the virtual appliance nodes should be available and running. All virtual appliance nodes should be available, running, and enabled.