After the recovery is complete, you must validate that the environment and application functionality is restored.

Procedure

  1. Log in to the vRealize Orchestrator node 1 appliance configuration Web interface.
  2. Restart the vRealize Orchestrator service from the Startup options page and wait for the service to start.
  3. Log in to the vRealize Orchestrator node 2 appliance configuration Web interface.
  4. Restart vRealize Orchestrator service from the Startup options page and wait for the service to start.
  5. Ensure that the two vRealize Orchestrator nodes are working in a cluster mode.
  6. Verify that every tab in the configuration is green.
  7. Log in to the vRealize Orchestrator server and verify that all the running tasks, policies, and workflows appear and continue running on the home page.